ISO 42024 Revision Checker
ISO/IEC/IEEE DIS 42024 · Enterprise, systems and software, Architecture fundamentals Stage 40.99 Planning date 15 Sep 2027, an estimate 35 terms · 20 clause areas · 9 annex sections

Home / Timeline

The stage history and what comes next

The draft entered the work programme on 1 December 2023 and reached stage 40.99 on 8 September 2026. Two committee drafts and a 12 week DIS ballot preceded approval. The next recorded steps are FDIS registration, the approval stage and publication; ISO records no date for any of them.

Stages as recorded by ISO
StageDateWhat it means
10.991 December 2023New project approved
20.001 December 2023New project registered in TC/SC work programme
30.0013 June 2024Committee draft (CD) registered
30.2020 August 2024CD consultation initiated
30.6016 October 2024Close of comment period
30.9222 January 2025CD referred back to Working Group
30.00b22 January 2025Committee draft (CD) registered, second round
30.20b27 March 2025CD consultation initiated, second round
30.60b24 May 2025Close of comment period, second round
30.9910 September 2025CD approved for registration as DIS
40.0012 September 2025DIS registered
40.2013 November 2025DIS ballot initiated: 12 weeks
40.606 February 2026Close of voting
40.998 September 2026Full report circulated: DIS approved for registration as FDIS
50.00Not reachedFinal text received or FDIS registered for formal approval (not reached)
60.00Not reachedInternational Standard under publication (not reached)
60.60Not reachedInternational Standard published (not reached)

What the history shows

The document took two committee draft rounds before the DIS was registered. The first CD consultation closed in October 2024 and the draft was referred back to the working group in January 2025, which is why the second round ran from March to May 2025. The DIS ballot then ran for 12 weeks from 13 November 2025 to 6 February 2026, and approval was recorded on 8 September 2026.

What to diarise

  • FDIS registration at stage 50.00: the text is fixed for formal approval.
  • Stage 50.20: the proof or FDIS ballot, eight weeks.
  • Stage 60.00: under publication.
  • Stage 60.60: published. This is the only stage that makes the standard available.

The watch checks the record for these transitions and emails the diff. The date on this site does not move because a stage slips; it is recalculated only when the stage record changes.

Last updated: 2026-10-21